Connect with us

News

TCN dismisses Kaduna electric’s claim on Jos transmission line

Published

on

The Transmission Company of Nigeria (TCN) has dismissed claims by Kaduna Electric that a fault on the 330kV Jos transmission line was responsible for the reduction in electricity supply across its franchise area.

In a statement issued on Thursday, TCN management said all 330kV transmission lines connected to Jos were fully operational and continuing to transmit bulk electricity.

The company described Kaduna Electric’s claim as “false and a deliberate misrepresentation of facts,” insisting that there had been no interruption in bulk power transmission through any of the 330kV lines supplying Jos.

TCN said the Jos–Lafia 330kV Line 2 circuit breaker, which had earlier been opened, was restored and had remained operational.

According to the company, the circuit breaker was opened on August 23 as part of a routine operation to control voltage and maintain stability across the national power grid.

TCN therefore rejected any suggestion that a fault on the Jos transmission network was responsible for the reported decline in electricity supply within Kaduna Electric’s franchise area.

“For the avoidance of doubt, all 330kV transmission lines connected to Jos are in service and transmitting bulk power,” the statement said.

“TCN recorded a lone incident on 23rd August 2026 at 03:30hrs, when the Jos–Lafia 330kV Line 2 circuit breaker was opened for voltage control. This was a routine operational action to maintain grid stability.”

According to the transmission company, the line was restored at 11:59 pm on August 24 and had remained in service since then.

“There has been no outage or disruption of bulk electricity transmission on any 330kV line supplying Jos attributable to TCN since that restoration,” it added.

The development followed an announcement by Kaduna Electric on Wednesday attributing reduced power supply across its franchise area to lower load allocation.

The electricity distribution company had said the reduction was mainly due to an outage of one generating unit at the Shiroro Generating Station and a fault on the 330kV Jos transmission line.

Kaduna Electric said the fault had resulted in Shiroro supplying Jos and its surrounding areas instead.

The company also said that, based on the National Control Centre Daily Load Allocation for August 25, it received 104 megawatts, comprising 54MW from the Mando 330kV Transmission Station and 50MW from the Birnin-Kebbi axis.

It said it was working with TCN on the equitable distribution of available power and monitoring efforts to restore supply.

However, TCN urged Kaduna Electric and other stakeholders to verify information with the transmission company before making public statements on transmission-related issues.

“We urge Kaduna Electric and other stakeholders to verify facts with TCN before issuing statements that misinform the public and create unnecessary anxiety,” it said.

TCN also advised electricity customers in Jos and its environs to disregard what it described as the misleading information, assuring that it remained committed to ensuring stable and reliable bulk power transmission to distribution companies nationwide.

Follow Very Nigerian WhatsApp Channel
For Verified Breaking News, Exclusive Reports, Trending Stories, And Real-time Updates.
CLICk HERE TO JOIN!
WhatsApp

Pearl Essien is a digital content creator and a graduate of the prestigious University of Calabar. With over four years of experience in writing, she specializes in crafting engaging stories that inform and inspire readers. Outside of her work, Pearl enjoys storytelling, reading, and playing table tennis, bringing the same curiosity and passion to her hobbies as she does to her writing.

Advertisement Follow Us on Google Discover
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Jobs / Vacancies1 day ago

Dangote Group opens 86 vacancies in Engineering, Finance, Logistics, HR, other fields

Jobs / Vacancies1 day ago

ECOWAS Bank opens applications for 2026 Young Professionals Programme

News24 hours ago

BREAKING: Police arrest former Imo governor Rochas Okorocha in Abuja

Politics13 hours ago

BREAKING: APC revises Tinubu Campaign Council, names Wike, Adeleke, Soludo as FCT, Rivers, Osun, Anambra coordinators (Full List)

Jobs / Vacancies1 day ago

Christopher University announces staff recruitment for academic, administrative positions

Jobs / Vacancies6 hours ago

Obafemi Awolowo University (OAU) opens 51 non-academic job vacancies in healthcare, other sectors – Apply Now

News1 day ago

Names of 68 lawyers elevated to SAN rank (Full list)

Editorials15 hours ago

2027: Economic hardship, appointments threaten Tinubu’s support in Northern Nigeria

Metro1 day ago

Ex-Akwa Ibom University SUG President dies at Enugu NYSC camp

Politics1 day ago

INEC disowns fake notice on six states as parties seek candidates’ inclusion

News1 day ago

BREAKING: Makinde appoints Wolekanle as new Chief of Staff

News1 day ago

JUST IN: Segun Ogunwuyi steps down as Makinde’s chief of staff

News16 hours ago

Real reason INEC excluded Adebutu, Pantami, others from final governorship candidates’ list

Politics1 day ago

BREAKING: Publish my name within 72hrs or else…. – Pantami give INEC ultimatum

Entertainment1 day ago

Ayra Starr makes African history, headlines NFL international game halftime show in London